Wednesday, January 21, 2009

Ambassador Cam, #42



A year after the destruction of the final piece of the Ambassador Hotel (the Cocoanut Grove, which had survived the initial tear-down), here's what's now on the site. So far, the frame looks a lot like the old hotel, as if it had been stripped to its studs.

According to the LAUSD's December "Monthly Program Status Report" for new construction, here's the latest news from the site:

• The Phase I K-3 project is currently 70% complete and is scheduled for occupancy in fall 2009. The methane mitigation system and underground utility rough-ins are complete. Classroom framing is complete, utility rough-ins are complete, and interior finishes are well under way. The structures for the central plant and parking facility are complete and finishes have commenced. Delivery and installation of central plant equipment is well under way. Site retaining walls and other structures are well under way.

• The MS/HS project is 38% complete, with school occupancy scheduled for fall 2010. Underground utilities, methane mitigation system and building foundations are nearly complete. Structural steel framing is complete, with a traditional "topping out" ceremony scheduled for November 21, 2008. Fireproofing, utility rough-ins and interior framing are well under way. Site retaining walls are well under way. Off-site work is well under way.




Meanwhile, here's the view from Catalina Street.