Wednesday, December 23, 2009

Ambassador Cam, #44 in a series



One final look this year at the new high school on the Ambassador Hotel site -- still without a name -- as it moves closer to completion. (The school is set to open in fall 2010.)

Here's the updated info on the site, from the LAUSD:

This project is the second phase of improvements for a comprehensive K-12 learning center being constructed at the site of the former Ambassador Hotel in the Mid-Wilshire District of Los Angeles. This project will provide 1,000 new middle school seats, 2,440 new high school seats, construction of a public park, restoration of the Cocoanut Grove and pylon structures, athletic facilities, and two-thirds of the site-wide methane mitigation system. Ultimate improvement of the Cocoanut Grove will include a 500-seat auditorium, and the restored Paul R. Williams Coffee Shop to be used as the staff/teacher lounge. This phase also provides four of the six commissioned art pieces for the site-wide public art program, commemorating the Ambassador Hotel's cultural and social history. The budget for the K-3 facility is included in the total budget for this project.


The school district cut the ribbon on the site's K-5 school back in October. The official press release:
CLALC#1 K-5 opened to more than 800 students on September 9, 2009.

"My father was a champion of those who suffered disadvantages in America. He was actively engaged in helping people help themselves through community action," said Maxwell Kennedy, son of Robert and Ethel Kennedy. "This new K-12 learning center will educate and empower our young people and their parents to fight for economic and social justice. I know of no better way to advance the living legacy of Robert Kennedy."

"The messages Robert F. Kennedy worked to deliver to us decades ago - that we can all be part of a change for a better world, a greater world - are alive with us as we celebrate the opening of not one, but two exciting new pilot schools here at Central Los Angeles Learning Center #1 K-5," Board President García said. "Years of commitment and struggle led by parents and the community come to fruition today as we mark profound change for students that now have two unique small schools dedicated to incorporating new and innovative methods of teaching."

The new elementary school site features two pilot schools (schools within the LAUSD given charter-like autonomy over curriculum): University California Los Angeles (UCLA) Community School (UCS) and New Open World (NOW) Academy. Both schools provide students with an opportunity to continue their education on the same school site once the middle and high school portions of the larger campus are completed.

Wednesday, March 11, 2009

Ambassador Cam, #43



Construction on the LAUSD's $572 million new high school on the site of the old Ambassador Hotel continues. The district says the new school (still unnamed) is on tap to open in fall 2010. Here's the fact sheet for the construction, which will encompass 391,840 square feet.



And here's the latest LAUSD monthly program status report on the project:
-- The Phase I K-3 project is currently 83% complete and is on schedule for occupancy in fall 2009. The methane mitigation system and underground utility rough-ins are complete. Classroom framing is complete; utility rough-ins are complete and interior fixtures and finishes are nearly complete. The structures for the central plant and parking facility are complete and finishes are nearly complete.

-- Delivery and installation of central plant equipment is complete and initial commissioning steps are underway. Site retaining walls and other structures are nearly complete. Permanent power is expected by the first week in March.

The school promises to deliver 1,000 new middle school seats and 2,440 new high school seats.

Wednesday, January 21, 2009

Ambassador Cam, #42



A year after the destruction of the final piece of the Ambassador Hotel (the Cocoanut Grove, which had survived the initial tear-down), here's what's now on the site. So far, the frame looks a lot like the old hotel, as if it had been stripped to its studs.

According to the LAUSD's December "Monthly Program Status Report" for new construction, here's the latest news from the site:

• The Phase I K-3 project is currently 70% complete and is scheduled for occupancy in fall 2009. The methane mitigation system and underground utility rough-ins are complete. Classroom framing is complete, utility rough-ins are complete, and interior finishes are well under way. The structures for the central plant and parking facility are complete and finishes have commenced. Delivery and installation of central plant equipment is well under way. Site retaining walls and other structures are well under way.

• The MS/HS project is 38% complete, with school occupancy scheduled for fall 2010. Underground utilities, methane mitigation system and building foundations are nearly complete. Structural steel framing is complete, with a traditional "topping out" ceremony scheduled for November 21, 2008. Fireproofing, utility rough-ins and interior framing are well under way. Site retaining walls are well under way. Off-site work is well under way.




Meanwhile, here's the view from Catalina Street.